large solar array on UVM Medical Center building in Williston
A rooftop solar array on the University of Vermont Medical Center building in Williston. Courtesy photo

[T]he stateโ€™s largest utility and a renewable energy trade group have reached an agreement over a proposed fee on new solar projects in certain parts of the state. But a solar company argues that those costs should instead be paid by all ratepayers.

The proposed $37 per kilowatt fee, which would go into effect this July, still has to be approved by the stateโ€™s utility regulator.

Vermont has one of the highest amounts of distributed solar generation compared to electricity consumed, or load, in the country. Green Mountain Power, the stateโ€™s largest electrical utility, has seen a 1,400% increase in net-metered solar among customers from 2010 to 2018.

But that increase in distributed electricity generation has come with growing pains. One challenge is something referred to in the utility world as โ€œtransmission ground fault overvoltage,โ€ or TGFOV.

As more solar comes online, the amount of generation compared to load has essentially reached a tipping point in certain parts of the state.

If more solar panels were to be added in those areas without upgrades, something like a tree falling on a line could lead to โ€œa much bigger issue,โ€ such as serious damage to transformers, substations and other components of the transmission system, explained Josh Castonguay, GMPโ€™s chief innovation officer.

Castonguay said the utility has been addressing the overvoltage issue over the past five or six years with transmission system upgrades.

โ€œBut whatโ€™s happened more recently is, at some point, a certain project โ€ฆ is kind of the straw that breaks the camelโ€™s back,โ€ he said.

Under current regulations, the full cost of those upgrades falls to the unlucky homeowner or developer whose proposed solar panels would put that part of the grid over the limit. The average upgrade costs $75,000 โ€” a cost GMP, developers and the state agree is prohibitively expensive for single projects to bear.

It’s created a backlog of projects that canโ€™t interconnect to the grid until one of them pays for the upgrade, according to a filing Castonguay made with the state Public Utility Commission.

GMP has determined that 70 of the utilityโ€™s 150 substations will eventually need upgrades to add more solar, said Castonguay.

In February, GMP made a filing with the PUC to charge $75/kW for projects planned in areas of the grid that need transmission upgrades. The fees would be pooled together to fund upgrades.

Renewable Energy Vermont, an industry trade group, filed requests for more specific information about the utilityโ€™s plan to address TGFOV. Executive Director Olivia Campbell Andersen said in an interview Thursday that REV initially had concerns about the โ€œhigh feeโ€ and lack of a clear timeline for completing the upgrades.

olivia campbell andersen
Renewable Energy Vermont Executive Director Olivia Campbell Andersen speaks at a rally in May 2016 promoting net metering. Courtesy photo

โ€œToo many Vermonters arenโ€™t able to generate their own electricity due to antiquated grid infrastructure,โ€ she said.

GMP and Renewable Energy Vermont reached an agreement earlier this month in the form of a $37 fee on new projects in areas that currently need upgrades or will need them in the future if more solar comes online. The utility would also have to provide a plan for prioritizing the upgrades and revisit the fee in two years.

Castonguay said that the utility was happy to have reached an agreement with REV. โ€œWe donโ€™t wantโ€ฆrooftop solar to be held up because of issues like this,โ€ he said.

Campbell Andersen said the revised proposal represents โ€œa more long-term solution in the GMP territory.โ€

The Department of Public Service, which had originally requested the PUC open a formal investigation into the proposal in March, agrees with the concept of spreading out the costs for upgrades among projects, said Ed McNamara, director of regulated utility planning.

โ€œThe main thing is this idea of a dollar per kilowatt fee for interconnections costs is brand new and hasnโ€™t been done before,โ€ he said.

McNamara added that the per kilowatt fee was essentially based on estimates of upgrade costs and how much generation would actually be installed. But the department feels the plan to revisit the fee down the line addresses those concerns, he said.

All Earth Renewables, a Willston-based solar company commented on the proposal, arguing that the costs associated with TGFOV upgrades โ€œshould be borne by ratepayers โ€” the collective beneficiaries of Vermontโ€™s renewable energy laws and policiesโ€ rather than by fees on solar projects.

โ€œThis approach reflects the manner in which the distribution grid of today and tomorrow must be available if a more electrified renewable-powered society is going to make a difference in addressing climate change,โ€ wrote All Earthโ€™s general counsel.

Campbell Andersen also said the TGFOV issue speaks to a broader need for grid modernization in an era of increased distributed electricity generation.

โ€œThe larger issue related to this is Vermonters are trying to rapidly accelerate to 100% renewable energy and weโ€™re working with great-grandmaโ€™s grid,โ€ she said.

GMP made a filing the same day saying it โ€œrespectfully disagreesโ€ that interconnection costs should be paid by customers.

โ€œWhile true that TGFOV constraints have become common and are not unique, that is not to say that responsibility for remedying these constraints should rest with the ratepayer,โ€ wrote Castonguay in a May 22 filing.

The Department of Public Service agrees with GMP that the upgrades are costs to connect to the grid, which are supposed to be paid by developers under state regulations, said McNamara.

Previously VTDigger's energy and environment reporter.