
[T]he state’s review of the proposed Vermont Yankee sale will take months longer than anticipated.
A revised schedule issued Monday by the Vermont Public Utility Commission shows that a second public hearing on the plant sale has been pushed to January, four months later than initially planned.
And it appears the commission’s review process could extend well beyond that, with technical hearings scheduled for late January in Montpelier and additional filings due at an undetermined later date.
But there appear to be no objections to the new schedule. A spokesman for the plant owner said the delays don’t affect the companyโs hope to sell the idled Vernon nuclear plant to New York-based NorthStar Group Services by the end of 2018.
โThis revised schedule continues to support the timing of the proposed transaction between Entergy Nuclear Vermont Yankee and NorthStar,โ said Joe Lynch, an Entergy senior government affairs manager.
Entergy administrators, who stopped power production at Vermont Yankee in December 2014, announced last November that they had a tentative deal for NorthStar to acquire the plant, its spent fuel and its decommissioning trust fund.

The state’s review was expected to be lengthy. And a schedule released in February confirmed that, as proceedings were scheduled through late 2017.
The change is being put down to the time needed for discovery, in which state agencies and other entities have asked detailed questions about the new Vermont Yankee decommissioning plan.
โThe schedule has been revised in response to the discovery process extending out beyond initial expectations,โ said Stephanie Hoffman, special counsel for the state Public Service Department. โAll of the dates in the schedule were moved to account for a nearly three-month discovery production period by (Entergy and NorthStar) that concluded last week.โ
In particular, the number and nature of documents that the two companies deemed โconfidentialโ seems to have slowed down the process. In fact, there were two levels of confidentiality granted due to NorthStar’s concerns about publicly disclosing proprietary information.
In addition to confidentiality issues, Windham Regional Commission Executive Director Chris Campany also pointed to โthe time necessary to process the sheer volume of information being presented.โ
Campany believes the state’s initial schedule may have been โambitious from the outset.โ
In early May, the Public Service Department threw up a stop sign by requesting an extension to file additional discovery requests. The department said it needed more time to review Entergy/NorthStar documents that initially had been withheld due to confidentiality issues.
Later that month, utility regulators agreed to that request and suspended the case’s entire schedule pending revisions.
Last week, Entergy and NorthStar jointly proposed a more lengthy schedule โafter reaching a consensus with the (Public Service Department) and other parties,โ Lynch said.
That led to Monday’s order from the commission.
Along with setting new deadlines for depositions, discovery requests and rebuttals, the commission tentatively set a public hearing for Jan. 4 in Vernon. That date depends on the availability of a meeting space.
That hearing โ which would be the second in the commission’s review process โ originally had been set for Sept. 5 or 6. The first hearing, held in April, drew a big crowd with many questions.
Both Hoffman and Campany said the timing of the second hearing is important, since it would take place after the submission of all evidence in the Vermont Yankee case but prior to technical hearings.
That timing, they said, has been preserved in the commission’s new schedule.
โThe idea is that this information will inform the public and the issues and questions that they bring to the public hearing, which can in turn inform lines of questioning by the parties as well as the Public Utility Commission,โ Campany said. โThose lines of questioning can also influence what evidence is entered into the record during the technical hearings.โ
