Editor’s Note: This story by Frances Mize was first published by the Valley News on Dec. 1.
THETFORD โ Upper Valley residents are facing the 18-month closure of the bridge that connects East Thetford with Lyme, New Hampshire, and tensions ran high at a meeting hosted by the New Hampshire Department of Transportation on Monday to address the refurbishment project.
But motorists and bicyclists will be left to simmer. The state of New Hampshire already has the $11 million project, funded mostly with federal dollars, under contract with a Massachusetts-based construction company.
Attendees piled into the auditorium in Anderson Hall at Thetford Academy to hear New Hampshire DOT officials walk through their decision-making process, as well as the construction time frame and traffic control plans.
The bridge over the Connecticut River is expected to be closed beginning in April or May 2023 for refurbishment until the scheduled completion date in late October 2024.
Listservs have been abuzz, an ad-hoc group has been formed, and a letter circulating between the two communities to call for halting the closure has garnered more than 500 signatures.
โThereโs been a lot of information circulated about this project thatโs not necessarily factual,โ Jennifer Reczek, the DOTโs project manager, said at the meeting. โI look at this as more of an education opportunity. The project is in construction, the contract has been awarded.โ
The Lyme-East Thetford Bridge, constructed in 1937, is the second priority in a lineup of almost 100 on New Hampshireโs โred list,โ which identifies the stateโs bridges most in need of repair.
The project, which will be handled by New England Infrastructure Inc., of Hudson, Massachusetts, will divert an estimated 2,200 cars a day during construction. Thetford Academy expects to be among the hardest-hit.
โHaving to detour to Orford or Hanover will, at a minimum, add up to an hour to our studentsโ travel time, reducing their ability to meet their educational needs on campus,โ Thetford Academy Board President Donna Steinberg wrote in a 2021 letter to Reczek.
Tara Pacht is an office manager at Long Wind Farm, a tomato farm that operates year-round in greenhouses and also hosts tai chi classes, and all but hugs the Thetford side of the bridge off of Route 5. She said the farm has been preparing for the closing for years.
โWe definitely agree collectively at Long Wind Farm that the bridge needs to be replaced,โ Pacht said in an interview.
The closing will impact their business, she said, but thatโs something she and her husband, Jesse, have anticipated since attending the first public meeting hosted by DOT in 2014.
โWe went to those meetings, and we see the updates when they come through. Itโs not a surprise for us,โ Pacht said. โIt will impact the tai chi business and our retail stand, but weโre hopeful that people will continue to still find us.โ
While the project is already under contract, attendees at Mondayโs meeting came equipped with apprehensions, criticisms and suggestions for how they thought it could be better pursued.
Eric Tadlock, executive director of Cedar Circle, expects a stymied cash flow for his business.
โBeing closed off from Lyme, we anticipate that weโre going to lose approximately $1 million worth of revenue from our Lyme customers,โ Tadlock said.
Reczek said sheโd been talking with town officials about the possibilities of adding some business signage โto help get the word out,โ but โthereโs not an ability to compensate (impacted businesses) directly.โ
Due to financial constraints, as well as limitations put on the project by environmental and historical resources in the vicinity of the project (the bridge itself was added to the National Register of Historic Places in 2020), Reczek said that building a temporary bridge has been ruled out.
The bridge closing โis in keeping with our typical means of addressing traffic control on these Connecticut River crossings,โ she said. โOur plan is to close the bridge, get this rehab work done as quickly as we can, and get the bridge reopened.โ
Others at the meeting were concerned about how the traffic diversion might impact already high-density commuter areas like Hanover, New Hampshire, which would be the nearest river crossing to the south and add an almost 18-mile, round-trip detour.
โUnfortunately thereโs not a whole lot we can do, and the Department of Transportation just said, โWeโre doing it,โ โ Peter Kulbacki, Hanoverโs Director of Public Works, said in an interview. โRight now we have to look at the morning commute. Thatโs about the time it will be the worst. But I donโt know that DOT ever really looked at that.โ
State transportation officials didnโt reach out to Hanover about the project, Kulbacki said.
Beyond concerns about the impact on businesses, as well as school and work schedules, some people were upset that the 470-foot steel bridge was merely being refurbished, not renovated with new features.
โIโm really disappointed that in the vast bureaucratic approach to what bridge we would get, that it was all environmental and historical concerns … that the needs of the community were never addressed,โ Thetford Selectboard member Li Shen said. โYouโre giving us a bridge thatโs an antique from the past. We need bicycle and pedestrian access as we try to stop climate change. You seem to be telling us the door is shut, itโs all decided, you canโt go back on this. But is there any way we can put a halt on this and reevaluate?โ
Shen elicited a smattering of applause from the audience.
โI was crossing (the Lyme-East Thetford bridge) twice on Saturday and I had to flatten myself in that extremely fearful position that many of you know here, to not be hit by cars and trucks along the way,โ Thetford resident Joanne Burns said.
To enhance safety, she suggested that the bridge could include signaling for pedestrians.
Reczek acknowledged that โthe strong needโ for some other connection between the two states in that area had been made clear, and that her department will work with regional planning commissions on that issue going forward.
โIt may or may not be able to happen as part of this project, but the sooner that gets planned the sooner we can potentially come up with a solution,โ Reczek said.
She closed the meeting by addressing the calls that the project be punted down the road, emphasizing that the federal money that makes up the bulk of the budget has an expiration date.
โWe have spent millions of dollars that would need to be paid back to (the Federal Highway Administration). So what happens if we donโt do this project? The best case would be construction in 2033,โ Reczek said. โAnd thereโs a very good risk that this bridge could be closed for years before weโd be able to find the funding to do something different.โ
Backing out of a contract with โno causeโ would be โunprecedented,โ Reczek said. It would almost guarantee that the bridge be closed for longer than currently slated, she added.
โI know this isnโt the answer that people are going to want to hear, but we have to make difficult decisions with the transportation funding we have,โ Reczek said.