
The plan โ which is under review by state and federal regulators โ is to downsize the former nuclear plant’s most secure zone from the current 10.5 acres to 1.3 acres encompassing a spent fuel storage facility.
Though the change wouldn’t take effect for more than a year, Entergy is asking the state Public Service Board for an expedited review: The company wants a decision by the end of August so the security modification project can begin the following month.
โReducing the size of the current protected area at VY station is a crucial part of the plantโs decommissioning process,โ George Thomas, a senior project manager at the Vernon plant, wrote in a memo submitted to the Public Service Board.
Entergy, which stopped power production at Vermont Yankee at the end of 2014, wants to accelerate the plant’s decommissioning by selling the site to New York-based NorthStar Group Services. NorthStar has pledged to clean up most of the site by 2030, whereas Entergy’s decommissioning plan could have taken up to 60 years.
Entergy and NorthStar want to complete the sale by the end of 2018, but the deal depends on approval by both the federal Nuclear Regulatory Commission and the state Public Service Board.
The end of 2018 is important for another reason: That’s the current deadline for moving all of Vermont Yankee’s radioactive spent fuel from a cooling pool into more secure storage inside sealed dry casks.

Eventually, all of the spent fuel will be stashed in 58 casks standing on two concrete pads. And that fuel storage area is the focus of Entergy’s new proposal to modify security.
Vermont Yankee’s current 10.5-acre protected area โ access to which is tightly controlled under 24-hour armed guard โ encloses multiple structures including the turbine, reactor and control room buildings.
The much smaller area to take effect in late 2018 would cover only the two fuel storage pads and a proposed new central alarm station building.
To protect the spent fuel, crews also would install new security facilities including a concrete vehicle barrier system; two fences with a paved โisolation zoneโ between them; and new lighting, cameras and intrusion detection equipment.
The project, while relatively small in scope, is supposed to have big benefits.
For one thing, the smaller security zone will allow decommissioning to โproceed in an efficient and orderly manner,โ Entergy’s attorneys wrote. Thomas said eliminating the larger protected area will allow decommissioning crews and vehicles to work โwithout the substantial burden and expense of having to enter and exitโ that area.
Money is another factor. The smaller security zone will allow Entergy to reduce its expenditures from Vermont Yankee’s decommissioning trust fund by about $1.2 million a month, administrators say.
The smaller area โwill require fewer security personnel to monitor and to maintain,โ the company says.
The need for control room operators, technicians and support staff also would be reduced.
The estimated savings include only personnel costs. It’s possible the downsizing of the secure area also could result in reduced insurance, taxes and utility bills, according to documents filed with the Public Service Board.
Those documents appeared Monday on the board’s electronic filing system website, known as ePSB. Officials said Entergy initially filed its request via hard copies in early May, and there had been a delay in posting them online.
Either way, Entergy is seeking a relatively quick turnaround by asking the board to rule on the request by the end of August. In his memo, Thomas said the company wants to get some important work done before next winter.
โThe project will be conducted almost entirely outdoors, so it is weather-sensitive,โ Thomas wrote. โIf Entergy VY does not receive authorization by Aug. 31, it may not be able to complete the underground work in 2017, which would extend the installation schedule.โ

The board last year authorized a second spent fuel pad at Vermont Yankee, and Entergy says the new security proposal simply is an extension of that decision because it is โclosely relatedโ to the fuel pad case and โis more modest in scope than the previously approved work.โ
From an aesthetic standpoint, Harry Dodson โ a Massachusetts landscape architect and an Entergy consultant โ wrote that the security project โwill add small new visual components to the site,โ but โthe changes are minor when considered against the visual backdrop of the far larger VY station industrial site.โ
Furthermore, a reduced security zone โwill result in a net reduction in visual impacts when the current larger protected area is removed during decommissioning,โ Dodson wrote.
Entergy’s proposed changes also are dependent on approval from the NRC.
The company has filed for a license amendment โto reduce the siteโs security plan once all of the Vermont Yankee spent nuclear fuel has been transferred to dry cask storage,โ NRC spokesman Neil Sheehan said.
Such a request โis normal for all permanently shutdown nuclear power plants,โ he said.
โWe are currently reviewing the submittal and are targeting completing the licensing action within one year,โ Sheehan added. โAgain, it is not needed until all of the fuel is moved to (dry casks), something which wonโt happen until at least mid- to late 2018.โ
