Business & Economy

$60M Brattleboro interstate bridge to open in March

I-91 bridge
Eric Foster, the Vermont Agency of Transportation’s resident engineer on the I-91 bridge project in Brattleboro, examines a gap still to be filled in the $60 million project as of last fall. File photo by Kristopher Radder/Brattleboro Reformer
BRATTLEBORO – In about a month, Interstate 91 drivers will get a firsthand look at a long-awaited $60 million bridge.

According to a schedule submitted to state legislators, two northbound lanes on the new I-91 bridge in Brattleboro are expected to open March 13.

One southbound lane will be available in late April, the state Agency of Transportation says. And all four lanes finally will be open in mid-June.

Given that the project and its accompanying traffic bottleneck have lasted much longer than anyone expected, officials say they’re happy that the end is near.

“I feel good about it, and I think VTrans feels good about it,” said Rep. Mollie Burke, P-Brattleboro, who is a member of the House Transportation Committee.

The House and Senate Transportation committees last week received an update from several Transportation Agency officials on the I-91 project, which began in 2013.

Lead contractor PCL Civil Constructors has been working since then to replace a deteriorated steel bridge with a 1,036-foot-long concrete structure that arcs over Route 30 and the West River. The company also is replacing a smaller interstate bridge over Upper Dummerston Road nearby.

The original completion date was in late 2015, but factors including permit delays, winter weather, excavation problems and labor shortages have been blamed for pushing the work into this year.

That means interstate traffic in the construction zone has been limited to two lanes for more than three years. Transportation officials have used a monitoring system to try to reduce bottlenecks, sometimes closing the Exit 3 on-ramps during heavy travel times.

Also, there have been sporadic lane restrictions and closures on Route 30 underneath the bridge.

Late last year, as crews prepared to join the hulking, cantilevered sections of the new bridge, PCL and transportation officials said they were hoping for some traffic to begin flowing over the structure in March.

I-91 bridge
The project nearly a year ago. File photo by Kristopher Radder/Brattleboro Reformer
That has held true, despite repeated heavy snows that have buffeted the work zone in recent weeks. Contractors are using multiple heaters to warm affected areas before performing structural work, said Eric Foster, the Transportation Agency’s resident engineer on the bridge project.

“That’s the downside to working in the winter: Everything’s got to be up to temperature,” Foster said in an interview Tuesday. “It takes a lot of extra work.”

Although the bridge is substantially complete, Foster stressed that there are “still a lot of little pieces to do.” That includes work on supporting structural “tendons” and expansion joints, along with installation of bridge railings and median barriers.

Even after all traffic is moved to the new bridge, PCL will have more work to tackle. The biggest job is removal of the old steel span that has been bearing all interstate traffic through the area.

At this point, state officials expect PCL will be completely finished before year’s end.

The size and scope of the project is illustrated by statistics in Foster’s legislative report. The bridge superstructure has required 14,000 cubic yards of concrete, and the construction site has swallowed 3 million pounds of rebar.

The unique design of the bridge – developed after aesthetic consultations with local residents – has been cited as one factor in the job’s duration and difficulty. “It’s obviously a really complicated project,” said Burke, who toured the site last year.

That doesn’t mean the AOT has taken the extended schedule in stride. Officials negotiated a settlement with PCL that reduced the contract value by nearly $1.38 million and insulated the state from delay-related costs.

All told, the project contract now stands at $60.2 million, according to the legislative report. That’s up from the original bid of $59.5 million, but officials say the increase was kept to a minimum due to the settlement.

“I think the state has come out pretty well, financially,” Burke said.

While acknowledging the project’s complications, both Burke and Foster praised the quality of the finished product.

“This is not your ordinary highway bridge,” Burke said. “This is a gateway to Vermont for a lot of people.”


If you read us, please support us.

Comment Policy

VTDigger.org requires that all commenters identify themselves by their authentic first and last names. Initials, pseudonyms or screen names are not permissible.

No personal harrassment, abuse, or hate speech is permitted. Comments should be 1000 characters or fewer.

We moderate every comment. Please go to our FAQ for the full policy.

Mike Faher

Recent Stories

  • Steve Baker

    Gee, to listen to the State you’d think this is some kind of miracle bridge, an engineering marvel.
    The original completion date was in late 2015 ? (fill in excuses here) but factors including
    permit delays, winter weather, excavation problems and labor shortages
    have been blamed for pushing the work into this year.

    What it exposes,
    – the state government isn’t competent enough to run a job this size
    – unable to vet and hire the right contractors
    – and after all this, “I feel good about it, and I think VTrans feels good about it,” said Rep. Mollie Burke, P-Brattleboro