Editorโ€™s note: This op-ed is by Don Keelan of Arlington.

The state of Vermont refers to it as Bennington NH 019-1 (5).ย ย Local officials refer to it as the Northern Segment of the Bennington Bypass.ย ย The rest of us refer to it as the Bennington Motor Vehicle Obstacle Course.

For four years, ever since construction on the Northern Segment of the bypass commenced, never does a week go by (except during the winter months) when the driving pattern of U.S. Route 7/Vt. Route 279 does not change.

Hundreds, if not thousands,ย  of those orange and white inverted plastic barrels are rearranged, directing traffic into newly created temporary driving lanes—literally yards away from enormous earth/rock moving equipment—and we are only at the two-thirds point, the western segment, of Vt. Route 279, completed in October 2004.

By southwestern Vermont standards, the Bennington Bypass would be the equivalent of what the โ€œBig Digโ€ was to Boston—when completed, ย the interchange, from an aerial perspective, will rival a Los Angeles, Calif., interchange.

According to the stateโ€™s Agency of Transporationย  Web site, discussion with local legislators and project manager and AOT official Jim Harris, the Bennington Bypass is a large undertaking.

The project had been conceived over 50 years ago (Harris has a newspaper article that dates back to 1926 addressing the bypass)—mainly to โ€œreduce delay, improve safety and decrease congestionโ€ in the Bennington area—especially so where the two major east/west and north/south roads intersect, Vt. Route 9 and U.S. Route 7.ย ย The goals are still the same today.

The three-mile Northern Segment, with a $95 million price tag, will direct traffic to the east from southbound U.S. 7 and eastbound Route 279, to Vt. Route 9, just outside of downtown Bennington,.ย ย According to the AOTs, this extraordinary cost per mile ($31.6 million) is in part due to:

a) ย  Relocating three high-tension power lines, 7,500 feet in length.

b) ย  Building five bridges, three of which are over 470 feet in length.

c) ย  ย Removing the dangerous rockslide at the earlier built Exit 2 on U.S. Route 7.

d) ย  ย Circumventing wetlands and access to Bald Mountain and the Long Trail.

Of course, what is not mentioned is the ripping out of previously built roadwork, realigning existing entrances and exit ramps and reworking a half- dozen existing bridges.

Another significant cost factor was the $3 million expended on the archeological excavation of a 4,000-year-old Native American village.ย ย I must be the only person in Bennington County who had been unaware of such a discovery. The recovered artifacts are presently being stored in a Burlington warehouse.ย ย The recovered artifacts will be put on display when the highwayโ€™s welcome center is built.

What has further complicated the design (and cost) of the Northern Segment is the fact that in 1999, the Legislature instructed the AOT to make provisions to build a welcome center within the junction of U.S. Route 7 and Vt. Route 279.ย ย The center will be built by the stateโ€™s Office of Buildings and General Services and operated by the Bennington Area Chamber of Commerce.

The $7 million center was to have been completed at the time of completion of the Northern Segment; not so, if started by next spring, it wonโ€™t open until late 2013.

And the โ€œrubโ€ with the proposed welcome center, there is no turnoff lane for northbound travelers coming through the Town of Bennington;ย  such a lane is too expensive, according to Harris.ย ย Northbound visitors, at the Kocher Drive intersection, will have to turn west onto Route 67, go past Wal-Mart and at Cinema 7, on Northside Drive, get back on eastbound Vt. Route 279 in order to enter the welcome center.ย ย This will be the case until the Southern Segment is built.

The design for the Southern Segment of the bypass is on hold—no funds have been allocated.ย ย If it is ever built, it will have a length of 3.2 miles and connect south U.S. Route 7 (near Fuller Road) heading northeast, to Vt. Route 9.

Its present benefit is that it is on the receiving end for 200,000 cubic meters of earth and rock that had been removed during the excavation of the Northern Segment.ย ย This quantity, according to Harris, would be like filling a regulation football field (100 by 54 yards) 15 stories high;ย  thank goodness there was a place to put the material.

When the three segments are completed, the Bennington Bypass will have cost approximately $206 million ($56 million for the western, $95 million for the northern and in todayโ€™s dollars, $55 million for the southern segments)—funded 80 percent by the federal government and 20 percent by Vermont.ย ย The engineering for the Southern Segment, if funded by the summer of 2012, will take approximately four years to design and get permitted—add another four years to build—if all goes well.

Should we have ever built the bypass? The final price tag is astounding, northbound visitors most likely will never visit the proposed welcome center and others will simply not visit Bennington and motor right on by. To be spending upwards of a quarter-billion dollars for a 10-mile road system to bypass a town of 15,000 residents makes no sense—and we ask why governments are in a fiscal mess?

The 1989 movie โ€œField of Dreamsโ€ has an often-quoted line, โ€œBuild it and they will come.โ€ย ย Letโ€™s hope the line for the Bennington Bypass will not be โ€œbuild it and they (the visitors) will go—-directly by Bennington.โ€