
In the latest back and forth with FEMA, the Shumlin administration apparently hopes the third time will be the charm. FEMA has twice denied the state and local requests for funding for bigger better culverts, and now the state is taking its case to Washington.
The culvert in question — a concrete โboxโ culvert in Townshend — is a test case that could have big budget implications for towns. Sue Minter, Vermontโs Irene Recovery officer, says Townshend, for example, will have to come up with the $100,000 difference if FEMA doesnโt approve the project for funding. In Mendon, the latest estimate for culvert repair costs not yet been covered by FEMA, is $400,000 to $500,000. (The townโs annual budget is $900,000.)
In all, about 40 towns could face a shortfall if the state is unsuccessful.
The total price tag is about $10 million.
Itโs unclear when FEMA will make a decision. The agency must respond in 90 days, but could ask for more information at that point, which would extend the deadline another 90 days. By that time, the Legislature will be wrapping up its work at the Statehouse.
Minter says towns are facing huge financial pressure, but itโs too early for the state to start talking about funding the difference until FEMA responds to the latest appeal.
โRight now we are pushing to maximize federal participation,โ Minter said. โCan the state find a way to pay for it? That will be a good conversation for the Legislature to have.โ
In the meantime, towns are bonding or taking out lines of credit for the projects, many of which have been completed or are under way.
Steve Jeffrey, executive director of the Vermont League of Cities and Towns, said the best outcome would be for the state to be successful in its appeal to Washington.
โWe donโt want to give up on the feds,โ but if the state isnโt successful, Jeffrey said, his organization will be lobbying the Legislature to pay for the additional costs. The state has required the installation of the larger culverts and โif the state is the one that is saying there no exception to the plan for state requirements there should be some state responsibility for helping towns with the difference.โ
A dispute over codes
Tropical Storm Irene wiped out 500 miles of roadways and washed out thousands of culverts in southern Vermont in August 2011, and federal, state and local governments scrambled last fall to put temporary infrastructure in place to ensure that communities wouldnโt remain isolated over the winter. Since then, FEMA and the state have reviewed 3,000 project worksheets in 200 towns.
Now towns are making permanent repairs to highway infrastructure. The box culverts are a key element in the stateโs long-term infrastructure fix for what officials see as an ongoing problem: climate change. The Agency of Natural Resources and the Agency of Transportation are planning for the next deluge that could destroy highway infrastructure and leave Vermonters stranded or exposed to dangerous situations. State officials say they required that towns build box culverts in an effort to build infrastructure that will survive the next big flood.
The federal agency has said it would reimburse towns for replacing existing culverts. These narrower culverts clogged or washed out during Irene. FEMA officials first rejected towns reimbursement requests for the larger culverts last spring because the state does not have uniform standards for culvert sizes.
Dave Mace, a spokesman for FEMA, says the federal agency has argued that the stateโs stream alteration permitting system is discretionary in nature. โThatโs the point of law that FEMA has been adhering to all along,โ Mace said.
The state has three different standards for stream permits. โThere is a level of discretion in applying those standards, in FEMAโs opinion,โ Mace said.
Mace said when the code or standard that an applicant is citing meets FEMAโs criteria โ including that it is not discretionary โ that the agency can be assured the code or standard is followed whether or not federal funds are available. The federal agency uses the same protocol across states, municipalities and counties nationwide to ensure โthere is an even playing field.โ
State attorneys are arguing that FEMAโs recommendations violate the agencyโs own environmental standards for minimizing floodplain development impacts. They also say in the appeal that the agency should follow standards set by the Army Corps of Engineers for โfish passage.โ
In a statement, the governorโs office says FEMAโs regional officials are taking โan unnecessarily stringent view of the law and are ignoring the fact that Townsend has chosen the least cost means of complying with state and federal standards.โ
โWe have to make smart choices with public funds, consistent with the law. In this case the Town of Townshend has done both,โ Gov. Peter Shumlin said. โWe are committed to rebuilding stronger post-Irene, and Vermontโs towns should not be denied FEMA reimbursement for meeting state infrastructure repair standards designed to withstand future storms.โ
Minter said the state is not only appealing the decision for towns in Vermont, but also attempting to set a national precedent.
โWe see this as a national policy issue,โ Minter said. โWe believe FEMA should be reimbursing states to the codes that set the stage for looking to future and mitigating future hazards, particularly in light of our changing climate.โ
Jeffrey says his organization, which represents more than 200 municipalities, agrees with the state that FEMA should pay for larger culverts so that when the next storm comes along, โtheyโre not back here next year replacing with a too small culvert.โ
โFrom our perspective, thereโs no choice,โ Jeffrey said. โItโs not discretionary. We had to have done it. It seems to meet the needs that FEMA wants to accomplish with its program so that theyโre not back here next year replacing with a too small culvert.โ
